Issues

  • According to the bids of three contractors, the Xactimate estimate of $440,000 was significantly lower than the amount needed to rebuild the home. Was the estimate provided by Farmers an accurate representation of the damage?
  • 90 days had passed since the incident. If estimates proved to be inaccurate, what steps needed to be taken to ensure the proper amount was reimbursed?
  • The house was 75 years old. Additions and adjustments were needed to make sure the building met today’s building code standards. Were these properly included in the estimate? Did the estimates substitute functional materials for original materials, frequently not as readily available today?

Solutions Applied

  • Using their own team of specialists, engineers and contractors, The Greenspan Co./Adjusters International team compiled an estimate and as a result concluded that the estimate of damages was significantly higher than what Farmers proposed – nearly 50% more. In order to support this analysis, they included the expert opinions of the Loughran’s own architect and contractor.
  • Greenspan Adjusters International, Inc. secured sub bids to support its position, presenting these to Farmers with its estimate. Through negotiations and persistence on the part of the Greenspan Adjusters International, Inc. team, Farmers acquiesced to the new bids as the actual replacement cost, increasing replacement cost from the initial $440,000 to $680,000.
  • Greenspan Adjusters International, Inc. team determined that code upgrades were not included in the initial Farmers assessment of the damage. To bring the building up to today’s safety standards would result in a $100,000 increase. In addition, three steel windows were damaged in the kitchen during the fire. Initially Farmers provided minimal funding for replacement, using stock window pricing. After consulting specialists, it was concluded that the windows needed to be custom made. Since these windows were throughout the house, it was argued that all of the home’s windows needed replacement so that they would all match as they did before the fire. This resulted in an additional $50,000 payment to the Loughrans.

Outcome

Greenspan Adjusters International, Inc. was able to determine the initial estimate for repairs was inaccurate, and secured an appropriate settlement for the Loughrans, almost doubling the initial offer of $440,000 to $830,000.

Were we to have another major loss due to fire or flood – God forbid – there is no question that I would hire Greenspan Adjusters International, Inc. to represent me immediately. I learned, after the fact, that the process would have gone even better had we brought in Greenspan Adjusters International, Inc. in from the beginning rather than after the insurer had made its initial determination of the amount it would pay.

Charles S. Loughran, Esq.